# The North Falls Offshore Wind Farm Order 2026, Paragraph 189: Monitoring


If following the results of any geophysical surveys carried out using multi-beam echo sounder survey , it is confirmed that cable exposure has occurred within the Area of Interest, the undertaker will notify the PLA as soon as reasonably practicable and in any event no later than 2 business days after the undertaker confirms any exposure has occurred.

---
Source: https://www.legislation.gov.uk/uksi/2026/567/schedule/14/paragraph/189 (the official version)
Page: https://openlegislation.uk/north-falls-offshore-wind-farm-order-2026/schedule-14/paragraph-189
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.