# The North Falls Offshore Wind Farm Order 2026, Paragraph 27: As built drawings


As soon as reasonably practicable following the completion of the construction of Works Nos. 4B or 4C within plots 01-001, 01-002, 01-004, 01-005 and 01-006, the undertaker must provide to the Agency as-built drawings in a form and scale to be agreed in writing between the undertaker and the Agency (acting reasonably) to show location and depths of the cable ducts as installed which must include identification markings on the sea defence.

---