# The North Falls Offshore Wind Farm Order 2026, Paragraph 85: Maintenance of the authorised development


(1) The undertaker must, prior to the commencement of any works of maintenance to the specified cable works, give National Highways 28 days’ notice in writing of the date on which those works will start unless otherwise agreed by National Highways, acting reasonably.
(2) If, for the purposes of maintaining the cable works or the SRN works, the undertaker needs to occupy any road space, the undertaker must comply with National Highways’ road space booking requirements and no maintenance of any works for which a road space booking is required may commence without a road space booking having first been secured.
(3) The undertaker must comply with any requirements that National Highways may notify to the undertaker, such requirements to be notified to the undertaker not less than 7 days in advance of the planned commencement date of the maintenance works.
(4) The provisions of paragraph 77 will apply to the opening of any part of the strategic road network following occupation of any road space under this paragraph.

---
Source: https://www.legislation.gov.uk/uksi/2026/567/schedule/14/paragraph/85 (the official version)
Page: https://openlegislation.uk/north-falls-offshore-wind-farm-order-2026/schedule-14/paragraph-85
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.