# The North Falls Offshore Wind Farm Order 2026, Paragraph 95: Build option 2A scenario


(1) Where the undertaker determines to proceed with build option 2A and the parties intend for additional ducts to be installed as either or both of Work Nos. 6B and 12B to be transferred to Five Estuaries then—
(a) the undertaker will consult and agree with Five Estuaries on its detailed design and construction methodology, including means of access, before any application for discharge of requirements necessary to carry out either or both of Work Nos. 6B and 12B is made to the relevant planning authority; and
(b) the undertaker will agree the route and specification of any permanent access to be used by both the undertaker and Five Estuaries prior to discharging any requirement for the detailed design of such accesses necessary to construct such access.
(2) Any agreement required under this paragraph must not be unreasonably withheld or delayed and any requests for amendment must have regard to the scope of the assessment set out in the Environmental Statement.

---
Source: https://www.legislation.gov.uk/uksi/2026/567/schedule/14/paragraph/95 (the official version)