# The North Falls Offshore Wind Farm Order 2026, Paragraph 20: Guillemot CIMP


Following consultation with the GCSG the guillemot CIMP must be submitted to, and approved by, the Secretary of State in consultation with the relevant SNCB and the relevant planning authority for the area in which the compensation measure is to be provided prior to the commencement of Work No. 1.

---
Source: https://www.legislation.gov.uk/uksi/2026/567/schedule/15/paragraph/20 (the official version)
Page: https://openlegislation.uk/north-falls-offshore-wind-farm-order-2026/schedule-15/paragraph-20
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

