# The North Falls Offshore Wind Farm Order 2026, Paragraph 44: RTD CIMP


Where the undertaker elects to submit a RTD CIMP under paragraph 44(1)(b) or 44(b)(c), the undertaker must form and administer the RTDCSG before carrying out any works to deliver the compensation measure under a RTD CIMP to be approved under this Part 4 of Schedule 15. The undertaker will invite representatives from the following organisations, as a minimum, to participate in the RTDCSG—
(a) Marine Management Organisation;
(b) the relevant SNCB;
(c) the relevant planning authority;
(d) the Royal Society for the Protection of Birds; and
(e) NatureScot.

---
Source: https://www.legislation.gov.uk/uksi/2026/567/schedule/15/paragraph/44 (the official version)
Page: https://openlegislation.uk/north-falls-offshore-wind-farm-order-2026/schedule-15/paragraph-44
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.