# The North Falls Offshore Wind Farm Order 2026, Paragraph 5: LBBG CIMP


(1) The LBCSG will develop a plan for the work of the LBCSG, to be submitted to and approved by the Secretary of State, which is to include—
(a) its terms of reference;
(b) details of its membership;
(c) details of the proposed schedule of meetings, reporting and review periods;
(d) a schedule for the preparation of the LBBG CIMP; and
(e) the dispute resolution mechanism and confidentiality provisions.
(2) The LBCSG must be convened and consulted on the proposed LBBG CIMP before any approval of the LBBG CIMP is sought by the undertaker under this paragraph.

---