# The North Falls Offshore Wind Farm Order 2026, Paragraph 11: Design parameters


The total length of the cable circuits in Work No. 1(b) and the area and volume of their cable protection (including cable crossings) must not exceed the following—
(1)
Parameter
(2)
Value
Maximum total length
170 km
Maximum protection area
204,000 m2
Maximum protection volume
119,000 m3

---