Paragraph 33 Completion of construction

Original text. Later amendments are not shown.

(1)

The undertaker must submit a close out report in writing to the MMO and the relevant SNCB within three months of the date of completion of construction. The close out report must confirm the date of completion of construction and must include the following details—

(a)

the final number of installed wind turbine generators; and

(b)

the installed wind turbine generator parameters relevant for ornithological collision risk modelling.

(2)

Following completion of construction, no further construction activities can be undertaken under this licence.