# The North Falls Offshore Wind Farm Order 2026, Paragraph 34: Completion of construction


(1) The undertaker must submit a close out report in writing to the MMO and the relevant SNCB within three months of the date of completion of construction. The close out report must confirm the date of completion of construction and must include the final number of installed offshore substation platforms.
(2) Following completion of construction, no further construction activities can be undertaken under this licence.

---