Paragraph 36 Cable and Scour Reporting

Original text. Later amendments are not shown.

The undertaker must submit a close out report to the MCA, Trinity House and the UK Hydrographic Office within three months of the date of completion of construction. The close out report must confirm the date of completion of construction and must include the following—

(a)

the final number of installed offshore substation platforms;

(b)

a plan of the layout of installed offshore substation platforms; and

(c)

latitude and longitude coordinates of the centre point of the location of each offshore substation platform, provided as Geographical Information System data referenced to WGS84 datum.