# The North Killingholme (Generating Station) (Amendment) Order 2026, Article 7: Amendments to Part 3 (Requirements) of Schedule 1 (Authorised development)


(1) Part 3 (Requirements) of Schedule 1 (Authorised development) is amended as follows.
(2) In paragraph 1—
(a) in the definition of “designated site”, for ““Post Combustion CCS Area”” substitute “Land Reserved for carbon capture readiness compliance””;
(b) after the definition of “operations area” insert—
““overlap areas” means the areas of Work No. 1 shown cross hatched green on the works plans;”; and
(c) omit the definition of “post-combustion CCS proposal” and substitute—
““post-combustion CCS proposal” means the CCS proposal not including Work No. 2a set out in the feasibility study dated 21 July 2025 (North Killingholme (Generating Station) Order – Non-Material Change Application 2025 Carbon Capture Readiness Compliance) certified by the Secretary of State for the purposes of this Order;”.
(3) After paragraph 52, insert—
“Work No. 1
53. Work Nos. 1(a), 1(b), 1(c), 1(d), 1(e) and 1(p) must not be carried out within the overlap areas.”.

---
Source: https://www.legislation.gov.uk/uksi/2026/445/article/7 (the official version)
Page: https://openlegislation.uk/north-killingholme-generating-station-amendment-order-2026/article-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.