# The North Killingholme (Generating Station) Order 2014, Paragraph 4: Detailed design

Extent: E+W+S

(1) No works within the relevant phase of the authorised development may commence until details of the following, which must accord with requirement 5, have been submitted and approved by the relevant planning authority—
(a) details of the siting, design, external appearance and dimensions of Work Nos. 1, 2a, 2b, 3b, 3c, 4, 6a, 6b and 7 comprised in the authorised development;
(b) details of the colour, materials, and surface finishes of Work Nos. 1, 2a, 2b, 4, and 7 comprised in the authorised development;
(c) details of Work No. 4 and any other vehicular circulation roads, parking, and hard standings comprised in the authorised development; and
(d) details of finished ground levels and heights of all permanent buildings and structures comprised in the authorised development which in respect of critical infrastructure, shall not be below 5.2 metres above ordnance datum.
(2) The authorised development shall be carried out and maintained in accordance with the approved details.

---
Source: https://www.legislation.gov.uk/uksi/2014/2434/schedule/1/paragraph/4 (the official version)
Page: https://openlegislation.uk/north-killingholme-generating-station-order-2014/schedule-1/paragraph-4
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.