# The North Killingholme (Generating Station) Order 2014, Paragraph 2: Applications made under requirement

Extent: E+W+S

(1) Where an application has been made to a discharging authority for any agreement or approval required by a requirement the discharging authority shall give notice to the undertaker of their decision on the application before the end of the decision period.
(2) For the purposes of sub-paragraph (1), the decision period is—
(a) where no further information is requested under paragraph 3, 5 weeks from the day immediately following that on which the application is received by the authority;
(b) where further information is requested under paragraph 3, 5 weeks from the day immediately following that on which further information has been supplied by the undertaker under paragraph 3; or
(c) such longer period as may be agreed by the undertaker and the discharging authority in writing before the end of the period in sub-paragraph (a) or (b).

---
Source: https://www.legislation.gov.uk/uksi/2014/2434/schedule/6/paragraph/2 (the official version)
Page: https://openlegislation.uk/north-killingholme-generating-station-order-2014/schedule-6/paragraph-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.