(1) The licence holder must only work and access the works site within a defined and marked out area thereby limiting personnel and plant access to the site.
(2) Co-ordinates (in WGS84) and plan diagrams of the work area and access routes must be submitted to the MMO at least 4 weeks prior to the commencement of works.
(3) The written approval of the co-ordinates and plan diagrams by the MMO is required prior to works commencing.

---
Source: https://www.legislation.gov.uk/uksi/2014/2434/schedule/7/paragraph/13 (the official version)
Page: https://openlegislation.uk/north-killingholme-generating-station-order-2014/schedule-7/paragraph-13
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.