(1) If any permanent or temporary alterations or additions to railway property, or any protective works under paragraph 5(4), are reasonably necessary during the construction of a specified work, or during a period of 12 months after the opening of any part of the authorised project that includes a specified work, in direct consequence of the construction of that specified work—
(a) such alterations and additions may be carried out by Network Rail; and
(b) if Network Rail gives to the undertaker reasonable notice of its intention to carry out such alterations or additions, the undertaker shall pay to Network Rail all costs reasonably and properly incurred in constructing those alterations or additions including, in respect of any such alterations and additions as are to be permanent, a capitalised sum representing the increase of the costs which may be expected to be reasonably incurred by Network Rail in maintaining, working and, when necessary, renewing any such alterations or additions.
(2) If during the construction of a specified work by the undertaker, Network Rail gives notice to the undertaker that Network Rail desires itself to construct that part of the specified work which in the opinion of the engineer is endangering the stability of railway property or the safe operation of traffic on the railways of Network Rail then, if the undertaker desires that part of the specified work to be constructed, Network Rail shall assume construction of that part of the specified work and the undertaker shall, notwithstanding any such approval of a specified work under paragraph 5(1), pay to Network Rail all reasonable expenses to which Network Rail may be put and compensation for any loss which it may suffer by reason of the execution by Network Rail of that specified work.
(3) The engineer shall, in respect of the capitalised sum referred to in this paragraph and paragraph 10(1)(a) provide such details of the formula by which those sums have been calculated as the undertaker may reasonably require.
(4) If the cost of maintaining, working or renewing railway property is reduced in consequence of any such alterations or additions, a capitalised sum representing such saving shall be set off against-any sum payable by the undertaker to Network Rail under this paragraph.

---
Source: https://www.legislation.gov.uk/uksi/2014/2434/schedule/8/part/3/paragraph/9 (the official version)
Page: https://openlegislation.uk/north-killingholme-generating-station-order-2014/schedule-8/part-3/paragraph-9
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.