(1)

Before commencing the construction of a tidal work the Company shall furnish to A.B.Ports for its approval, which it shall not unreasonably withhold, plans of the work showing the general mode of construction and such work shall not be constructed otherwise than in accordance with such plans as may be approved by A.B.Ports or as may be determined as hereinafter provided and all such works shall be executed to the reasonable satisfaction of A.B.Ports.

(2)

When submitting plans to the Secretary of State pursuant to article 12 (Tidal works not to be executed without approval of Secretary of State) of this Order, the Company shall send a copy thereof to A.B.Ports and the Company shall, on receipt of approval of plans or of any conditions or restrictions imposed under that article, send a copy to A.B.Ports.

(3)

In the event of A.B.Ports failing to express its disapproval of any plans within 56 days after they have been delivered to it under this paragraph, it shall be deemed to have approved them.