# The North Killingholme Haven Harbour Empowerment Order 1994, Paragraph 3


The Company shall give to A.B.Ports not less than fourteen days' written notice of their intention to commence the construction of a tidal work and, not more than fourteen days after completion of such construction, shall give to A.B.Ports written notice of such completion.

---