# The North Lincolnshire Green Energy Park Order 2025, Part 2: PARAMETERS TABLE

Extent: E+W+S

(1)
Component
(2)
Maximum dimensions
(m)
(2)
Maximum height above Finished Floor Level (FFL)
(m)
(2)
Maximum height AOD
(m)
ERF (Work No. 1)Tipping hall87.5 x 603137.6
Bunker hall92 x 404349.6
Boiler hall105 x 605561.6
Flue gas treatment hall41 x 604551.6
Turbine hall80 x 372531.6
Bottom ash hall37 x 372531.6
Transformer compound52 x 221016.6
Switchyard93 x 441014.6
Offices and admin facilities30 x 1004349.6
Fire water tank11.3 diameter19.325.9
Fire water pumphouse6 x 66.513.1
Gatehouses32 x 12511.6
Visual barriers4.511.1
ERF stack windshield (Work No. 1A)10 diameter120126.6
Back up boilers stack windshield (Work No. 1A)3 diameter5359.6
Back-up generator stack (Work No. 1A)0.85 diameter5561.6
Carbon capture utilisation and storage facility (Work No. 1B)79 x 665056.6
Carbon dioxide storage tanks (Work No. 1B)28 x 202026.6
Visitor centre (Work No. 1C)41 x 361619.05
Elevated walkway (Work No. 1 and 1C)700 x 41217.05
Air-cooled condensers/Air blast chillers (Work No. 1D)75 x 355056.6
RHTF and CBMF (Work No. 2)process building and storage areas280 x 1302530.1
Admin buildings62 x 102126.1
Rail Infrastructure (Work No. 3)Footbridge No. 155.385
Footbridge No. 248.561
Access road (Work No. 5)5.2
Plastic recycling facility (Work No. 6)Pre-processed material storage65 x 351013.9
Heat exchange building35 x 171518.9
Post processed storage5 x 16.41518.9
Electrical rooms15 x 71013.9
Process building130 x 802528.9
Admin building62 x 102124.9
Hydrogen electrolyser (Work No. 7)Northern Gas AGI60 x 6059.6
Northern hydrogen production and storage facility100 x 25812.6
Vehicle refuelling station
(Work No. 8)
95 x 8012.515.5
Hydrogen refuelling station (Work No. 8)Southern Gas AGI60 x 60510.1
Southern hydrogen production and storage facility100 x 25811.6
Battery storage facility (Work No. 9)115 x 588.511.5

---
Source: https://www.legislation.gov.uk/uksi/2025/362/schedule/1/part/2 (the official version)
Page: https://openlegislation.uk/north-lincolnshire-green-energy-park-order-2025/schedule-1/part-2/enacted
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.