# The North Lincolnshire Green Energy Park Order 2025, Paragraph 2: Commencement and phasing of the authorised development and notices

Extent: E+W+S

(1) The authorised development must not be commenced after the expiration of five years from the date this Order comes into force.
(2) The authorised development must not be commenced until a written scheme setting out the proposed phasing of the authorised development has been submitted to and approved by the relevant planning authority and the approved phasing scheme must be complied with thereafter.
(3) The undertaker must notify the relevant planning authority within seven days of each of the following events occurring—
(a) the start of commissioning of any part of the authorised development; and
(b) the coming into operation of any part of the authorised development.

---
Source: https://www.legislation.gov.uk/uksi/2025/362/schedule/2/paragraph/2 (the official version)
Page: https://openlegislation.uk/north-lincolnshire-green-energy-park-order-2025/schedule-2/paragraph-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.