(1) Notice of the intended completion of commissioning of the plastic recycling facility (Work No. 6) must be given to the relevant planning authority where practicable prior to such completion. ...
(2) Prior to the coming into operation of Work No. 1 (ERF) the plastic recycling Facility (Work No. 6) must have been constructed and commissioned.
(3) The plastic recycling facility (Work No. 6) shall only treat plastic waste received from suppliers who are also supplying the undertaker with refuse derived fuel used to fuel the combustion system in Work No. 1 (b).

---
Source: https://www.legislation.gov.uk/uksi/2025/362/schedule/2/paragraph/24 (the official version)