The North London Heat and Power Generating Station Order 2017 (“the Order”)f1, which granted development consent within the meaning of the Planning Act 2008f2, contains correctable errors within the meaning of the Actf3.

In accordance with paragraph 1(5)(a) of Schedule 4 to the Act, before the end of the relevant period, as defined in paragraph 1(6)(a) of Schedule 4 to the Act, the Secretary of State received a written request from the applicantf4 for the correction of errors and omissions in the Order.

In accordance with paragraph 1(7) of Schedule 4 to the Act, the Secretary of State has informed the relevant local planning authorities that the request has been received.

The Secretary of State, in exercise of the powers conferred by section 119 of, and paragraphs 1(4) and (8) of Schedule 4 to, the Act, makes the following Order.

Annotations

Footnotes

f1

S.I. 2017/215.

f2

2008 c.29.

f3

As provided for in Schedule 4 to the Act.

f4

As defined in paragraph 4 of Schedule 4 to the Act.