# The North London Heat and Power Generating Station Order 2017, Paragraph 7

Extent: E+W+S

(1) Subject to sub-paragraphs (2) and (3), if by reason, or in consequence, of the construction of any such works referred to in paragraph 4(2), any damage is caused to any apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of a statutory undertaker, or there is any material interruption in any service provided, or in the supply of any goods, by any statutory undertaker, the undertaker must—
(a) bear and pay the proper and reasonable cost actually incurred by that statutory undertaker in making good such damage or restoring the supply; and
(b) make proper and reasonable compensation to that statutory undertaker for any other reasonable and proper expenses, loss, damages, penalty or costs actually incurred by the statutory undertaker,
by reason or in consequence of any such damage or interruption.
(2) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption as far as it is attributable to the act, neglect or default of a statutory undertaker, its officers, servants, contractors or agents.
(3) A statutory undertaker must give the undertaker reasonable prior written notice of any claim or demand, and no settlement or compromise may be made without the consent of the undertaker.

---
Source: https://www.legislation.gov.uk/uksi/2017/215/schedule/13/part/2/paragraph/7 (the official version)
Page: https://openlegislation.uk/north-london-heat-and-power-generating-station-order-2017/schedule-13/part-2/paragraph-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.