# The North London Heat and Power Generating Station Order 2017, Paragraph 6: Acquisition of land

Extent: E+W+S

(1) Regardless of any provision in this Order or anything shown on the land plans or contained in the book of reference, the undertaker may not exercise any power to acquire any land interest or apparatus or override any easement or other interest of the statutory undertaker otherwise than by agreement (such agreement not to be unreasonably withheld or delayed).
(2) As a condition of agreement between the parties referred to in sub-paragraph (1), prior to the carrying out of any part of the authorised works (or in such other timeframe as may be agreed between the statutory undertaker and the undertaker) that are subject to the requirements of this Part that will cause any conflict with or breach the terms of any easement or other land interest of the statutory undertaker relating to the Order land or affects the provisions of any enactment or agreement regulating the relations between the statutory undertaker and the undertaker in respect of any apparatus laid or erected in land belonging to or secured by the undertaker within the Order land, the undertaker must as the statutory undertaker reasonably requires enter into such deeds of consent upon such terms and conditions as may be agreed between the statutory undertaker and the undertaker acting reasonably and which must be no less favourable on the whole to the statutory undertaker unless otherwise agreed by the statutory undertaker.
(3) The undertaker and the statutory undertaker agree that where there is any inconsistency or duplication between the provisions set out in this Part relating to the relocation or removal of apparatus (including but not limited to the payment of costs and expenses relating to such relocation or removal of apparatus) and the provisions of any existing easement, rights, agreements and licences granted, used, enjoyed or exercised by the statutory undertaker and/or other enactments relied upon by the statutory undertaker as of right or other use in relation to the apparatus, then the provisions of this Part prevail.
(4) Any agreement or consent granted by the statutory undertaker under any other paragraph of this Part must not be taken to constitute agreement under sub-paragraph (1).

---
Source: https://www.legislation.gov.uk/uksi/2017/215/schedule/13/part/5/paragraph/6 (the official version)
Page: https://openlegislation.uk/north-london-heat-and-power-generating-station-order-2017/schedule-13/part-5/paragraph-6
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.