# The North London Heat and Power Generating Station Order 2017, Paragraph 21: Decommissioning and demolition of the electricity and heat generating station

Extent: E+W+S

(1) Within 24 months of the electricity and heat generating station comprising Works No. 1a ceasing to be used for waste management purposes, a plan for the decommissioning, demolition and removal of the electricity and heat generating station must be submitted to the relevant planning authority for approval.
(2) Subject to obtaining the necessary consents and approvals, the decommissioning, demolition and removal of the electricity and heat generating station must be implemented in accordance with the plan approved under paragraph (1).
(3) On the first anniversary of the operational site ceasing to be used for waste management purposes, the undertaker must notify the relevant planning authority of the same.

---
Source: https://www.legislation.gov.uk/uksi/2017/215/schedule/2/paragraph/21 (the official version)
Page: https://openlegislation.uk/north-london-heat-and-power-generating-station-order-2017/schedule-2/paragraph-21
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.