# The North London Heat and Power Generating Station Order 2017, Paragraph 9: BREEAM rating

Extent: E+W+S

(1) No stage of the authorised development is to commence until, in relation to any new buildings within that stage (excluding temporary structures and temporary buildings)—
(a) a pre-construction stage consultation with the Building Research Establishment (BRE) (in accordance with the BRE’s requirements) has been carried out; and
(b) proposals identifying the range of options to achieve the British Research Establishment Environmental Assessment Methodology (BREEAM) rating of no less than “very good” have been submitted to and approved in writing by the relevant planning authority.
(2) The relevant stage must be carried out in accordance with the details approved under paragraph (1).

---
Source: https://www.legislation.gov.uk/uksi/2017/215/schedule/2/paragraph/9 (the official version)