In the London Borough of Enfield.
Access from Advent Way to the south of the Edmonton EcoPark as shown on drawings C_0012 Rev 01 and C_0013 Rev 00 of the works plans.
4(g)
In the London Borough of Enfield.
Access from Meridian Way to Ardra Road as shown on drawing C_0013 Rev 00 of the works plans.
4(s)
In the London Borough of Enfield.
Access from Walthamstow Avenue to the south of Lower Hall Lane into the temporary laydown area as shown on drawings C_0012 Rev 01 and C_0014 Rev 01 of the works plans.
5(j)
In the London Borough of Enfield.
Access from Advent Way to the south of Lee Park Way as shown on drawings C_0012 Rev 01 and C_0014 Rev 01 of the works plans.
4(t)
In the London Borough of Enfield.
Access from Lee Park Way to the south of the temporary laydown area shown on drawings C_0012 Rev 01 and C_0014 Rev 01 of the works plans.
5(i)
In the London Borough of Enfield.
Access from the northern end of Deephams Farm Road as shown on drawing C_0012 Rev 01 of the works plans.
4(k)
In the London Borough of Enfield.
Access from Lee Park Way into the Edmonton EcoPark as shown on drawings C_0012 Rev 01 and C_0014 Rev 01 of the works plans.
4(i)

---
Source: https://www.legislation.gov.uk/uksi/2017/215/schedule/9 (the official version)
Page: https://openlegislation.uk/north-london-heat-and-power-generating-station-order-2017/schedule-9
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.