In carrying out and maintaining the authorised development the undertaker may—
(a) deviate laterally from the lines or situations of the authorised development shown on the works plans to the extent of the limits of deviation within the Order limits relating to each numbered work shown on those plans and carry out construction and maintenance activities for the purposes of the authorised development anywhere within the Order limits; and
(b) deviate vertically from the levels of the authorised development—
(i) to any extent not exceeding 2 metres upwards; or
(ii) to any extent downwards as may be found to be necessary or convenient.

---
Source: https://www.legislation.gov.uk/uksi/2016/818/article/4 (the official version)