# The North Wales Wind Farms Connection Order 2016, Paragraph 6: Appeals

Extent: E+W+S

In this Schedule—
“relevant authority” means the relevant planning authority, relevant highway authority, traffic authority, street authority, or the owner of a watercourse, sewer or drain as may be appropriate to the consent, agreement or approval sought;
“appeal documentation” means—
(a)a statement of the grounds of appeal;
(b)a copy of any relevant application to the relevant authority;
(c)a copy of any relevant permit;
(d)a copy of any relevant correspondence between the undertaker and the relevant authority and/or NRW; and
(e)a copy of the decision or notice that is the subject of the appeal; and
“appeal parties” means the undertaker and the relevant authority.

---
Source: https://www.legislation.gov.uk/uksi/2016/818/schedule/10/paragraph/6 (the official version)
Page: https://openlegislation.uk/north-wales-wind-farms-connection-order-2016/schedule-10/paragraph-6
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.