# The North Wales Wind Farms Connection Order 2016, Paragraph 14: Piling

Extent: E+W+S

(1) No stage of the authorised development which requires piling activities must commence until a piling method statement for that stage of the authorised development has been submitted to and approved by the relevant planning authority.
(2) Piling must be carried out in accordance with the approved piling method statement.

---
Source: https://www.legislation.gov.uk/uksi/2016/818/schedule/2/paragraph/14 (the official version)