# The North Wales Wind Farms Connection Order 2016, Paragraph 4: Stages of authorised development

Extent: E+W+S

(1) No authorised development is to commence until a written scheme setting out all the stages of the authorised development has been submitted to and approved by the relevant planning authority, such scheme to include the following details—
(a) confirmation whether the authorised development is to be carried out in a single stage or multiple stages;
(b) if multiple stages, the chronological order of such stages; and
(c) the date of commencement of each stage.
(2) The authorised development must be carried out in accordance with the approved scheme.

---