# The North Wales Wind Farms Connection Order 2016, Paragraph 9: Highway works

Extent: E+W+S

(1) No work to construct or alter any permanent or temporary means of access to a highway to be used by vehicular traffic must commence until, following consultation with the relevant highway authority, written details of the design and layout of that means of access has been submitted to and approved by the relevant highway authority.
(2) The highway accesses must be constructed in accordance with the details approved under sub-paragraph (1).

---
Source: https://www.legislation.gov.uk/uksi/2016/818/schedule/2/paragraph/9 (the official version)
Page: https://openlegislation.uk/north-wales-wind-farms-connection-order-2016/schedule-2/paragraph-9
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.