# The North Wales Wind Farms Connection Order 2016, Part 2: TEMPORARY ALTERATION OF LAYOUT

Extent: E+W+S

Table 2
(1)
Area
(2)
Street subject to alteration of layout
(3)
Description of alteration
Denbighshire
Hafodty Ddu Road
Creation of new southern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 1) between points A and B to provide temporary access to numbered work 1A during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Denbighshire
Hafodty Ddu Road
Creation of new northern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 1) between points A and B to provide temporary access to numbered work 1A during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Denbighshire
Hafodty Ddu Road
Extend existing western access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 1) between points C1 and C2 to provide temporary access to numbered work 1A during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Denbighshire
Hafodty Ddu Road
Extend existing eastern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 1) between points C2 and C3 to provide temporary access to numbered work 1A during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Denbighshire
Access track from Hafodty Ddu Road
Creation of temporary stoned track comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 1) between points C1/C2 and D to provide temporary access to numbered work 1A during construction.
Denbighshire
Access track from Hafodty Ddu Road
Creation of temporary stoned track comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 1) between points C2/C3 and E to provide temporary access to numbered work 1A during construction.
Denbighshire
Hafodty Ddu Road
Creation of new western access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 1) between points J and K to provide temporary access to numbered work 1A during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Denbighshire
Hafodty Ddu Road
Creation of new eastern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 1) between points J and K to provide temporary access to numbered work 1A during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Denbighshire
Hafodty Ddu Road
Creation of new access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 2) between points L1 and L2 to provide temporary access to numbered work 1A during construction and for maintenance. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Denbighshire
Access track from Hafodty Ddu Road
Creation of temporary stoned track comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 2) between points L1/L2 and M to provide temporary access to numbered work 1A during construction.
Denbighshire
Nantglyn to Saron Road (B5435)
Creation of new southern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 2) between points P and Q to provide temporary access to numbered work 1A during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Denbighshire
Nantglyn to Saron Road (B5435)
Creation of new northern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 2) between points P and Q to provide temporary access to numbered work 1A during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Denbighshire
Bwlch Road
Extend existing southern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 3) between points T2 and U1 to provide temporary access to numbered work 1A during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Denbighshire
Bwlch Road
Upgrade existing northern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 3) between points T2 and U1 to provide temporary access to numbered work 1A during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Denbighshire
Prion Road
Extend existing access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 3) between points X1 and X2 to provide temporary access to numbered work 1A during construction and for maintenance. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Denbighshire
Access track off Prion Road
Creation of temporary stoned track comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 3) between pointsX1/X2 and Y to provide temporary access to numbered work 1A during construction.
Denbighshire
Denbigh to Cerrigydrudion Road (B4501)
Extend existing southern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 4) between points AB1 and AB2 to provide temporary access to numbered work 1A during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Denbighshire
Denbigh to Cerrigydrudion Road (B4501)
Extend existing northern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 4) between points AD1 and AD2 to provide temporary access to numbered work 1A during construction and for maintenance. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Denbighshire
Access track off Denbigh to Cerrigydrudion Road (B4501)
Creation of temporary stoned track comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 4) between pointsAD1/AD2 and AE to provide temporary access to numbered work 1A during construction.
Denbighshire
Denbigh to Nantglyn Road
Creation of new access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 5) between points AH1 and AH2 to provide temporary access to numbered work 1A during construction and for maintenance. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Denbighshire
Access track off Denbigh to Nantglyn Road
Creation of temporary stoned track comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 5) between points AH1/AH2 and AI to provide temporary access to numbered work 1A during construction.
Denbighshire
Denbigh to Nantglyn Road
Creation of new access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 5) between points AJ and AK to provide temporary access to numbered work 1A during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Conwy
Ffordd Gwaenynog (Bodeiliog Road)
Extend existing eastern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 6) between points AO and AP to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Conwy
Ffordd Gwaenynog (Bodeiliog Road)
Upgrade existing western access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 6) between points AO and AP to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Conwy
Lon Llewelyn (A543)
Extend existing southern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 6) between points AU2 and AV to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Denbighshire
Lon Llewelyn (A543)
Extend existing southern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 6) between points AV and AW to provide temporary access to numbered work 1A during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Conwy
Lon Llewelyn (A543)
Creation of new northern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 6) between points AU2 and AV to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Denbighshire
Lon Llewelyn (A543)
Creation of new northern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 6) between points AV and AW to provide temporary access to numbered work 1A during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Denbighshire
Access track from Lon Llewelyn (A543)
Creation of temporary stoned track comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 6) between points AX1/AX2 and AY to provide temporary access to numbered work 1A during construction.
Denbighshire
Access track from Leger Bach
Creation of temporary stoned track comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 6) between points BC and BB to provide temporary access to numbered work 1A during construction.
Conwy
Access track from Leger Bach
Creation of temporary stoned track comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 6) between points BB and BD to provide temporary access to numbered work 1B during construction.
Denbighshire
Access track from Leger Bach
Creation of temporary stoned track comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 6) between points BD and BE to provide temporary access to numbered work 1A during construction.
Conwy
Henllan to Groes Road (B5428)
Creation of new southern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 8) between points BH and BI2 to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Conwy
Henllan to Groes Road (B5428)
Creation of new northern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 8) between points BH and BI2 to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Conwy
Eriviat Bach Road
Creation of new southern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 8) between points BJ and BK2 to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Conwy
Eriviat Bach Road
Creation of new northern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 8) between points BJ and BK2 to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Conwy
Henllan to Llansannan Road (B5382)
Creation of new southern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 9) between points BN2 and BO to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Conwy
Henllan to Llansannan Road (B5382)
Extend existing northern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 9) between points BN2 and BO to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Conwy
Henllan to Cefn Berain Road
Extend existing access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 10) between points BR1 and BR2 to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Conwy
Access track from Henllan to Cefn Berain Road
Creation of temporary stoned track comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 10) between points BR1/BR2 and BS to provide temporary access to numbered work 1B during construction.
Conwy
Henllan to Cefn Berain Road
Extend existing southern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 10) between points BT2 and BU to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Conwy
Henllan to Cefn Berain Road
Extend existing northern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 10) between points BT2 and BU to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Conwy
Cefn Berain to Bontnewydd Road
Extend existing southern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 10) between points BV and BW2 to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Conwy
Cefn Berain to Bontnewydd Road
Creation of new northern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 10) between points BV and BW2 to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Conwy
Henllan to Llannefydd Road
Creation of new northern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 10) between points CD1 and CD2 to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Conwy
Henllan to Llannefydd Road
Upgrade existing eastern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 11) between points CB2 and CE1 to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Conwy
Henllan to Llannefydd Road
Extend existing access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 11) between points CB1 and CA1 to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Conwy
Bontnewydd Road
Upgrade existing southern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 11) between points CF and CG to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Conwy
Bontnewydd Road
Upgrade existing northern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 11) between points CF and CG to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Conwy
Bontnewydd Road
Extend existing northern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 11) between points CH and CI2 to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Denbighshire
Groesffordd Marli to Cefn Meiriadog Road
Creation of new southern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 13) between points CR and CS to provide temporary access to numbered work 1A during construction.
Denbighshire
Groesffordd Marli to Cefn Meiriadog Road
Extend existing northern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 13) between points CR and CS to provide temporary access to numbered work 1A during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Denbighshire
Groesffordd Marli to Glascoed Road
Extend existing access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 13) between points CT1 and CT2 to provide temporary access to numbered work 1A during construction and for maintenance. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows.
Denbighshire
Access track from Groesffordd Marli to Glascoed Road
Creation of temporary stoned track comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 13) between points CT1/CT2 and CU to provide temporary access to numbered work 1A during construction.

---
Source: https://www.legislation.gov.uk/uksi/2016/818/schedule/3/part/2 (the official version)
Page: https://openlegislation.uk/north-wales-wind-farms-connection-order-2016/schedule-3/part-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.