# The Northampton Gateway Rail Freight Interchange Order 2019, Paragraph 5: Payments

Extent: E+W+S

(1) The undertaker must fund the whole of the cost of the county highway works and all costs incidental to the county highway works and must also pay to the local highway authority in respect of each phase of the county highway works a sum equal to the whole of any costs and expenses which the local highway authority incur, including costs and expenses for using external staff and resources as well as costs and expenses of using in-house staff and resources in relation to the county highway works and arising out of them and their implementation, including—
(a) the checking and approval of all design work carried out by or on behalf of the undertaker for that phase;
(b) costs in relation to agreeing the programme of works for that phase;
(c) the carrying out of the inspection of that phase; and
(d) all administrative costs in relation to paragraphs (a), (b) and (c),
together comprising “the estimated costs”).
(2) The undertaker must pay to the local highway authority upon demand and prior to such costs being incurred the total costs that the local highway authority believe will be properly and necessarily incurred by the local highway authority in undertaking any statutory procedure or preparing and bringing into force any traffic regulation order or orders necessary to carry out or for effectively implementing the county highway works provided that this sub-paragraph does not apply to the making of any orders which duplicate orders contained in this Order.
(3) The undertaker and the local highway authority must agree a schedule of the estimated costs to be incurred pursuant to sub-paragraph (1) in respect of each phase prior to the commencement of that phase.
(4) The undertaker must make the payments referred to in sub-paragraph (1) as follows—
(a) the undertaker must pay a sum equal to the agreed estimated costs to the local highway authority prior to the local highway authority undertaking those tasks in respect of any phase of the county highway works;
(b) if at any time or times after the payment in respect of a phase referred to in paragraph (a) has become payable, the local highway authority reasonably estimates that the costs in respect of that phase referred to in paragraph (1) above will exceed the estimated costs for that phase, it may give notice to the undertaker of the amount by which it then reasonably estimates those costs will exceed the estimated costs (“the excess”) and the undertaker must pay to the county highway authority within 28 days of the date of that notice a sum equal to the excess.
(5) Within 91 days of the issue of the final certificate for each phase of the county highway works pursuant to paragraph 7 of this Part of this Schedule the local highway authority must give the undertaker a final account of the costs referred to in sub-paragraph (1) and within 28 days from the expiry of the 91 day period—
(a) if the account shows a further sum as due to the local highway authority the undertaker must pay to the local highway authority the sum shown due to it in that final account; and
(b) if the account shows that the payment or payments previously made have exceeded those costs the local highway authority must refund the difference to the undertaker.
(6) If any payment due under any of the provisions of this Part of this Schedule is not made on or before the date on which it falls due the party from whom it was due must at the same time as making the payment pay to the party to whom it was due interest at 1% above the rate payable in respect of compensation under section 32 (rate of interest after entry on land) of the 1961 Act for the period starting on the date upon which the payment fell due and ending with the date of payment of the sum on which interest is payable together with that interest.

---
Source: https://www.legislation.gov.uk/uksi/2019/1358/schedule/13/part/3/paragraph/5 (the official version)
Page: https://openlegislation.uk/northampton-gateway-rail-freight-interchange-order-2019/schedule-13/part-3/paragraph-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.