# The Northampton Gateway Rail Freight Interchange Order 2019, Paragraph 6: Design and phasing of highway works

Extent: E+W+S

The undertaker must complete the highway works identified in column (1) of the table below by no later than the stage of the authorised development set out in column (3) of the table below or such alternative later stage or event as agreed by the relevant body identified in column (4).
(1)
Works as described in Schedule 1
(2)
Description
(3)
Stage of Development
(4)
Relevant Body
Works No. 7(1)
A508 dualling and main site access roundabout
To be completed prior to the occupation of first warehouse to be occupied
Local highway authority
Works No. 8(1), (2) and (3)
M1 Junction 15 improvements including A45
To be completed prior to the occupation of first warehouse to be occupied
Highways England
Works No. 9(1), (2) and (3)
Saxon Avenue, C67 Watering Lane and Collingtree Footpath Bridge (highway works)
To be completed prior to the occupation of first warehouse to be occupied
Local highway authority
Works No. 11(1)
M1 Junction 15A improvements
Subject to requirement 31 to be completed prior to the opening to traffic of the A508 Roade Bypass (Works No. 13)
Highways England
Works No. 11(2)
M1 Junction 15A improvements (A5123)
Subject to requirement 31 to be completed prior to the opening to traffic of the A508 Roade Bypass (Works No. 13)
Local highway authority
Works No. 12(1)
A508 Blisworth Road junction improvement including footway improvements
To be completed prior to the opening to traffic of the A508 Roade Bypass (Works No. 13)
Local highway authority
Works No. 13
A508 Roade Bypass
To be completed within the earliest of—
(i) 2 years of occupation of first warehouse to be occupied; or
(ii) 4 years from the commencement of Works No. 8
Local highway authority
Works No. 14
A508/C26 Rookery Lane/ Ashton Road junction improvement
To be completed prior to the opening to traffic of the A508 Roade Bypass (Works No. 13)
Local highway authority
Works No. 15
A508/C85 Pury Road junction improvement
To be completed prior to the opening to traffic of the A508 Roade Bypass (Works No. 13)
Local highway authority
Works No. 16(1) and (2)
Knock Lane/Blisworth Road (Parish of Roade) improvements
To be completed prior to the opening to traffic of the A508 Roade Bypass (Works No. 13)
Local highway authority
Works No. 17
A508 Grafton Regis improvements
To be completed prior to the opening to traffic of the A508 Roade Bypass (Works No. 13)
Local highway authority

---
Source: https://www.legislation.gov.uk/uksi/2019/1358/schedule/2/part/1/paragraph/6 (the official version)