# The Northumberland County Council (A1 – South East Northumberland Link Road (Morpeth Northern Bypass)) Development Consent Order 2015, Article 3: Development consent etc. granted by the Order

Extent: E+W

(1) Subject to the provisions of this Order, including the requirements, the undertaker is granted development consent for the authorised development to be carried out within the Order limits.
(2) Subject to article 5 (limits of deviation) the works in Schedule 1 (authorised development) may only be constructed in the lines and situations shown on the works plans and in accordance with the levels shown on the sections.

---
Source: https://www.legislation.gov.uk/uksi/2015/23/article/3 (the official version)