# The Northumberland County Council (A1 – South East Northumberland Link Road (Morpeth Northern Bypass)) Development Consent Order 2015, Paragraph 14: Contamination

Extent: E+W

(1) If, during the construction of the authorised development, contaminated land not previously identified in the environmental statement is found within the Order limits then no further works or actions relating to the authorised development are to be engaged or carried out (unless otherwise approved by the relevant planning authority) until an investigation and remediation scheme has been submitted to and approved by the relevant planning authority; and the scheme must include details of—
(a) how the contaminated land is to be identified and assessed;
(b) where remediation is required by the scheme, the remediation measures;
(c) timescales for carrying out the remediation measures; and
(d) any ongoing monitoring or mitigation requirements.
(2) Where remediation measures are required by the investigation and remediation scheme then the remediation measures must be carried out no later than the times stipulated in the investigation and remediation scheme and in accordance with the investigation and remediation scheme.
(3) In this requirement, expressions used both in this requirement and section 78A (preliminary) of the Environmental Protection Act 1990 have the same meaning as in that section.

---
Source: https://www.legislation.gov.uk/uksi/2015/23/schedule/2/paragraph/14 (the official version)
Page: https://openlegislation.uk/northumberland-county-council-a1-south-east-northumberland-link-road-morpeth-northern-bypass-development-consent-order-2015/schedule-2/paragraph-14
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.