# The Northumberland County Council (A1 – South East Northumberland Link Road (Morpeth Northern Bypass)) Development Consent Order 2015, Schedule 9: LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN

Extent: E+W

(1)
Location
(2)
Number of land shown on land plans
(3)
Purpose for which temporary possession may be taken
(4)
Relevant part of the authorised development
County of Northumberland
Plots 2a, 10c, 10k, 15e and 19a
Contractors’ storage area for topsoil and other materials.
All works.
Plot 2b
Contractors’ temporary access to the works.
West of A1 at Fairmoor.
Plot 6b
Contractors’ temporary working area.
Footpath diversion Lancaster Park to St. Leonard’s underpass.
Plot 7b
Contractors’ storage area for topsoil and other materials.
All works.
Plots 8b and 19b
Areas for siting and use for contractors’ site compounds.
West Lane End Farm and Pegswood Moor Farm.
Plot 12a
Contractors’ temporary working area.
Fulbeck Lane.
Plot 15f
Construction and use of haul road.
All works.
Plot 17a
Construction and use of haul road and storage of topsoil and other materials.
All works.

---
Source: https://www.legislation.gov.uk/uksi/2015/23/schedule/9 (the official version)
Page: https://openlegislation.uk/northumberland-county-council-a1-south-east-northumberland-link-road-morpeth-northern-bypass-development-consent-order-2015/schedule-9
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.