# The Northumberland Line Order 2022, Part 1: STREETS FOR WHICH A SUBSTITUTE IS TO BE PROVIDED


(1)
Area
(2)
Highway/Street to be stopped up
(3)
Extent of stopping up (as shown on the rights of way plans)
(4)
New highway/street to be substituted (as shown on the rights of way plans)
County of Northumberland
A1061
The irregular shaped sections of vehicular highway to the east and west of Newsham level crossing shown as being stopped up on sheet 11 of the rights of way plans.
The diverted section of the A1061 crossing the railway on an overbridge to the south of the existing alignment shown as being new vehicular highway on sheet 11.
Footpath 300/162
Between points P53 and P54 (sheet 11).
New public right of way on foot between points P54 and P54a (sheet 11) along a new access track to be constructed at this location in accordance with a planning permission to be granted by Northumberland County Council.
Bridleway 300/016
Between points P76 and P78 (sheet 12).
Bridleway between points P76 and P77 (sheet 12).
Metropolitan Borough of North Tyneside
Backworth 13
Between points P15 and P19 (sheet 2).
Footpath between points P17 and P19 (sheet 2).
Backworth 2
Between points P25 and P26 (sheet 3).
Footpath between points P25 and P26 (sheet 3).
Backworth 2
Between points P26 and P27 (sheet 3).
Footpath between points P26 and P27 (sheet 3).

---
Source: https://www.legislation.gov.uk/uksi/2022/820/schedule/3/part/1 (the official version)
Page: https://openlegislation.uk/northumberland-line-order-2022/schedule-3/part-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.