# The Nottingham Express Transit System Order 2009, Paragraph 21

Extent: E+W

In relation to a work which is a specified work because of its proximity to or effect on a sewer, the plans to be submitted to the specified undertaker under paragraph 20 shall be detailed plans describing—
(a) the exact position of the specified work;
(b) the level at which it is proposed to be constructed or renewed;
(c) the manner of its construction or renewal;
(d) the position of all sewers within 15 metres of the specified work or upon which the specified work will impose a load; and
(e) by way of detailed drawings, every alteration proposed to be made to any such sewer.

---
Source: https://www.legislation.gov.uk/uksi/2009/1300/schedule/12/paragraph/21 (the official version)