# The Nutrient Action Programme Regulations (Northern Ireland) 2019, Paragraph 1

Extent: N.I.

If an application of organic manure (including livestock manure) or chemical fertiliser to steeply sloping land is proposed, a risk assessment must be undertaken in addition to meeting all relevant requirements of these Regulations. The factors set out in Table 1 shall be considered in making this risk assessment. Table 2 shall be consulted to ascertain whether fertiliser application is permitted.
Table 1
Fertiliser application to steeply sloping ground – risk assessment factors
Factor
Risk
Liquid organic manures
Solid organic manures
Chemical fertiliser
Distance from spreading area to waterway other than lake
High
less than 20 metres
less than 20 metres
less than 5 metres
Medium
20 – 30 metres
20 – 30 metres
5 – 10 metres
Low
greater than 30 metres
greater than 30 metres
greater than 10 metres
Distance from spreading area to lake
High
less than 30 metres
less than 30 metres
less than 10 metres
Medium
30 – 40 metres
30 – 40 metres
10 – 15 metres
Low
greater than 40 metres
greater than 40 metres
greater than 15 metres
Level of fertiliser applied
High
more than 25m3/ha
more than 25 tonnes/ha
greater than 120 kg/N/ha
Medium
15 – 25m3/ha
15 – 25 tonnes/ha
80 – 120 kg/N/ha
Low
less than 15m3/ha
less than 15 tonnes/ha
less than 80 kg/N/ha
Soil conditions
High
very wet, compacted soil
very wet, compacted soil
very wet, compacted soil
Medium
wet, poached soil
wet, poached soil
wet, poached soil
Low
dry, firm trafficable soil
dry, firm trafficable soil
dry, firm trafficable soil
Forecast weather conditions for next 48 hours
High
heavy rainfall (more than 4 mm per hour)
heavy rainfall (more than 4 mm per hour)
heavy rainfall (more than 4 mm per hour)
Medium
moderate rainfall (0.5 – 4 mm per hour)
moderate rainfall (0.5 – 4 mm per hour)
moderate rainfall (0.5 – 4 mm per hour)
Low
low rainfall (less than 0.5 mm per hour)
low rainfall (less than 0.5 mm per hour)
low rainfall (less than 0.5mm per hour)
Arable land only – time to incorporation
High
more than 48 hours
more than 5 days
n/a
Medium
12 – 48 hours
3 – 5 days
n/a
Low
less than 12 hours
less than 3 days
n/a
Table 2
Risk assessment determination
Risk level
Number of factors applicable
Is the land application of fertiliser permitted
High Risk
One or more factors
No
Medium Risk
Two or more factors
No
One factor
Yes
Low Risk
One or more factors
Yes

---
Source: https://www.legislation.gov.uk/nisr/2019/81/schedule/4/paragraph/1 (the official version)
Page: https://openlegislation.uk/nutrient-action-programme-regulations-northern-ireland-2019/schedule-4/paragraph-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.