# The Oaklands Farm Solar Park Order 2025, Paragraph 12: Battery safety management plan (BSMP)

Extent: E+W

(1) Prior to the commencement of Work No. 2 a battery safety management plan (BSMP) must be submitted to and approved by the local planning authority.
(2) The submitted BSMP must either accord with the outline BSMP or detail such changes as the undertaker considers are required.
(3) In the event that the submitted BSMP proposes changes to the outline BSMP the local planning authority must not approve the BSMP until it has consulted with Derbyshire Fire and Rescue Service.
(4) The BSMP must be implemented as approved and maintained throughout the construction, maintenance, operation and decommissioning of the authorised development.

---
Source: https://www.legislation.gov.uk/uksi/2025/739/schedule/1/paragraph/12 (the official version)
Page: https://openlegislation.uk/oaklands-farm-solar-park-order-2025/schedule-1/paragraph-12
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.