# The Oaklands Farm Solar Park Order 2025, Paragraph 16: Fencing and other means of enclosure

Extent: E+W

(1) No phase of the authorised development may commence until written details of all proposed permanent and temporary fences, walls or other means of enclosure of the connection works for that phase have been submitted to and approved by the local planning authority as part of the detailed design approval required by requirement 5(1).
(2) For the purposes of requirement 16(1), “commence” includes any site preparation works.
(3) Any construction site must remain securely fenced in accordance with the approved details at all times during construction of the authorised development.
(4) Any temporary fencing must be removed on completion of the phase of construction of the authorised development for which it was used.
(5) Any approved permanent fencing must be completed before completion of the authorised development.
(6) No site preparation works are to be commenced until written details of all proposed temporary fences, walls or other means of enclosure for the site preparation works have been submitted to and approved by the local planning authority.
(7) Any proposed permanent or temporary fences, walls or other means of enclosure must be carried out in accordance with the approved details.

---
Source: https://www.legislation.gov.uk/uksi/2025/739/schedule/1/paragraph/16 (the official version)
Page: https://openlegislation.uk/oaklands-farm-solar-park-order-2025/schedule-1/paragraph-16
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.