# The Oaklands Farm Solar Park Order 2025, Schedule 6: LAND IN WHICH ONLY NEW RIGHTS ETC. MAY BE ACQUIRED

Extent: E+W

In this Schedule—
“access rights” means rights over land to—
(a) alter, improve, form, maintain, retain, use (with or without vehicles, plant and machinery), remove, reinstate means of access to the authorised development including visibility splays and road widening and to remove impediments (including vegetation) to such access;
(b) pass and repass on foot, with or without vehicles, plant and machinery (including rights to lay and use any temporary surface or form a temporary compound) for all purposes in connection with the authorised development; and
(c) restrict and remove the erection of buildings or structures, restrict the altering of ground levels, restrict and remove vegetation and restrict the planting of trees or carrying out operations or actions (including but not limited to blasting and piling) which may obstruct, interrupt or interfere with the exercise of the rights or damage the authorised development;
“cable rights” means rights over land to—
(a) install, use, support, protect, inspect, alter, remove, replace, retain, renew, improve and maintain electrical underground cables, earthing cables, optical fibre cables, data cables, telecommunications cables and other services, works associated with such cables including bays, ducts, protection and safety measures and equipment, and other apparatus and structures;
(b) remain, pass and repass on foot, with or without vehicles, plant and machinery (including rights to lay and use any temporary surface or form a temporary compound) for all purposes in connection with the authorised development; and
(c) restrict and remove the erection of buildings or structures, restrict the altering of ground levels, restrict and remove vegetation and restrict the planting of trees or carrying out operations or actions (including but not limited to blasting and piling) which may obstruct, interrupt or interfere with the exercise of the rights or damage the authorised development;
“substation connection rights” means rights over land to—
(a) install, use, support, protect, inspect, alter, remove, replace, retain, renew, improve and maintain electrical cables, earthing cables, optical fibre cables, data cables, telecommunications cables and other services, works associated with such cables including bays, ducts, protection and safety measures and equipment, and other apparatus and structures and to connect such cables and services to the National Grid Drakelow substation;
(b) remain, pass and repass on foot, with or without vehicles, plant and machinery (including rights to lay and use any temporary surface or form a temporary compound) for all purposes in connection with the authorised development;
(c) restrict and remove the erection of buildings or structures, restrict the altering of ground levels, restrict and remove the planting of trees or carrying out operations or actions (including but not limited to blasting and piling) which may obstruct, interrupt or interfere with the exercise of the rights or damage the authorised development; and
(d) install, use, support, protect, inspect, alter, remove, replace, retain, renew, improve and maintain soft landscaping measures.
(1) Plot numbers(s)
(2) Work No.
(3) Purpose for which rights may be acquired and restrictive covenants imposed
01-012, 01-013, 01-014, 01-015, 01-016, 01-017, 01-018, 01-019, 01-020, 01-021, 01-022, 01-023, 01-024, 01-025, 01-026, 01-027, 01-028, 01-029, 01-030, 02-034, 02-035, 02-038, 02-039, 02-040, 02-041, 02-042, 02-044, 02-046, 02-049
6
Access rights
02-043, 02-047, 02-050, 03-058, 03-059
01-015, 01-019, 01-020, 01-021, 01-022, 02-040, 02-041, 02-042, 02-043, 02-044, 02-046, 02-047, 02-049, 02-050, 03-059
7
Access rights and cable rights
01-012, 01-013, 01-014, 01-015, 01-016, 01-017, 01-018, 01-019, 01-020, 01-024, 01-028, 01-030, 02-031, 02-032, 02-033, 02-035, 02-036, 02-037, 02-038, 02-040, 02-041, 02-042, 02-043, 02-046, 02-047
8
Access rights
02-040, 02-041, 02-042, 02-043, 02-046, 02-047
4
Cable rights
01-030, 02-031, 02-032, 02-033, 02-035, 02-038, 02-040, 02-043, 02-046, 02-047
4a
Cable rights
01-012, 01-013, 01-014
4b
Cable rights
01-001, 01-002, 01-003, 01-004, 01-007, 01-008, 01-009, 01-010, 01-011
4c
Cable rights
01-004, 01-010, 01-011
5
Substation connection rights
01-001, 01-002, 01-004, 01-007, 01-008, 01-009
5a, 5b
Access rights

---
Source: https://www.legislation.gov.uk/uksi/2025/739/schedule/6 (the official version)