# The Offshore Installations (Offshore Safety Directive) (Safety Case etc.) Regulations 2015, Paragraph 6: Design notification for production installations to be established during transitional period


Where a production installation is to be established on or after the commencement date but before 19th July 2016, the 2005 regime applies to the preparation and sending to the Executive of the design notification for that installation.

---
Source: https://www.legislation.gov.uk/uksi/2015/398/schedule/14/paragraph/6 (the official version)
Page: https://openlegislation.uk/offshore-installations-offshore-safety-directive-safety-case-etc-regulations-2015/schedule-14/paragraph-6
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.