Particulars of any combined operations which may involve the installation, including—
(a) a summary of the arrangements in place for co-ordinating the management systems of all duty holders involved in any such combined operation;
(b) a summary of the arrangements in place for a joint review of the safety aspects of any such combined operation by all duty holders involved, which must include the identification of hazards with the potential to cause a major accident and the assessment of risks which may arise during any such combined operation;
(c) the plant likely to be used during any such combined operation; and
(d) the likely impact any such combined operation may have on the installations involved.

---
Source: https://www.legislation.gov.uk/uksi/2015/398/schedule/7/paragraph/19 (the official version)
Page: https://openlegislation.uk/offshore-installations-offshore-safety-directive-safety-case-etc-regulations-2015/schedule-7/paragraph-19
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.