Where a well operation is to be carried out from a non-production installation or a vessel (not being an installation)—
(a) particulars of—
(i) the meteorological and oceanographic conditions to which that installation or, as the case may be, vessel may foreseeably be subjected;
(ii) the depth of water; and
(iii) the properties of the seabed and subsoil at the location at which the well operation will be carried out; and
(b) a description of how the well operator and—
(i) the owner of the installation; or
(ii) the operator and owner of the vessel,
involved in the well operation will co-ordinate their management systems so as to reduce the risks from a major accident to comply with the relevant statutory provisions.

---
Source: https://www.legislation.gov.uk/uksi/2015/398/schedule/9/paragraph/10 (the official version)
Page: https://openlegislation.uk/offshore-installations-offshore-safety-directive-safety-case-etc-regulations-2015/schedule-9/paragraph-10
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.