# The Offshore Installations (Safety Case) Regulations 1992, Paragraph 13


Sufficient particulars to demonstrate that the design of the installation, its plant and the pipe-lines connected to it is such that the risks from a major accident are at the lowest level that is reasonably practicable.

---
Source: https://www.legislation.gov.uk/uksi/1992/2885/schedule/2/paragraph/13 (the official version)
Page: https://openlegislation.uk/offshore-installations-safety-case-regulations-1992/schedule-2/paragraph-13
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.