# The Offshore Installations (Safety Case) Regulations 1992, Paragraph 6


A description of the operations on the well or, in the case of a fixed installation, of the operations involved in the drilling of the well, and a programme of works which includes—
(a) the dates on which the operations are expected to commence and finish; and
(b) the intended operational state of the well at the end of the operations.

---
Source: https://www.legislation.gov.uk/uksi/1992/2885/schedule/6/paragraph/6 (the official version)
Page: https://openlegislation.uk/offshore-installations-safety-case-regulations-1992/schedule-6/paragraph-6
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.