The Order establishes, under section 22 of the Petroleum Act 1987, safety zones having a radius of 500 metres from the specified point around the eleven installations (which are subsea installations) specified in the Schedule to this Order to be stationed in waters to which section 21(7) of that Act applies (these include territorial waters and waters in areas designated under section 1(7) of the Continental Shelf Act 1964 (c. 29)).

Made under: Petroleum Act 1987 (Section 22, Section 24)

PDFs: Printed copy https://openlegislation.uk/offshore-installations-safety-zones-order-2015/pdf/uksi_20150407_en.pdf

## Introductory text

Offshore Installations
Made 23rd February 2015
Coming into force in accordance with article 1(2)
The Secretary of State makes this Order—
(a) in exercise of the powers conferred by section 22 of the Petroleum Act 1987; and
(b) for the purpose of giving effect to proposals submitted to him by the Health and Safety Executive under section 24(2A) of that Act.

## 1 Citation and commencement

(1) This Order may be cited as the Offshore Installations (Safety Zones) Order 2015.
(2) This Order comes into force on 18th March 2015 except for article 2(1) which comes into force as provided in article 2(2).

## 2 Establishment of safety zones

(1) A safety zone is established around each installation specified in column 1 of the Schedule (being an installation to be stationed in waters to which subsection (7) of section 21 of the Petroleum Act 1987 applies) having a radius of five hundred metres, as respects that installation, from the point which has the co-ordinates of latitude and longitude according to the World Geodetic System 1984 specified in columns 2 and 3 of the Schedule.
(2) Paragraph (1) comes into force, as respects each installation specified in column 1 of the Schedule, when the installation arrives at its station.

## Signature

Signed by authority of the Secretary of State for Work and Pensions
Freud
Parliamentary Under Secretary of State
Department for Work and Pensions
23rd February 2015

## INSTALLATIONS

(1)
Name or other designation of the offshore installation
(2)
Latitude
(3)
Longitude
Catcher Area Development Project, Block 28/9a, Burgman Field
56°44.55′ North
00°40.61′ East
Catcher Area Development Project, Block 28/9a, Catcher Field
56°46.30′ North
00°46.30′ East
Catcher Area Development Project, Block 28/9a, Varadero Field
56°48.37′ North
00°42.30′ East
Cawdor Manifold and Production Wells, Block 30/13a, Cawdor Field
56°32.35′ North
02°34.47′ East
Cayley/Montrose Intermediate Towheads, Block 22/17s, Cayley Field
57°26.16′ North
01°18.42′ East
Cladhan Field Development Project, Block 210/9a and 210/30a, Cladhan Field
61°08.86′ North
00°47.17′ East
Flyndre Manifold and Production Wells, Block 30/14a, Flyndre Field
56°33.55′ North
02°37.85′ East
Golden Eagle Northern Drill Centre, Block 14/26a, Golden Eagle Field
58°00.79′ North
00°55.38′ West
Shaw Drill Centre, Block 22/22a, Montrose Field
57°17.81′ North
01°21.77′ East
Shaw Water Injection, Block 22/22a, Montrose Field
57°17.37′ North
01°22.31′ East
Western Isles SDC Development Project, Block 210/24a, Barra Field
61°11.74′ North
00°43.67′ East

## Explanatory note

(This note is not part of the Order)
The Order establishes, under section 22 of the Petroleum Act 1987, safety zones having a radius of 500 metres from the specified point around the eleven installations (which are subsea installations) specified in the Schedule to this Order to be stationed in waters to which section 21(7) of that Act applies (these include territorial waters and waters in areas designated under section 1(7) of the Continental Shelf Act 1964 (c. 29)).
Vessels, which for this purpose include hovercraft, submersible apparatus and installations in transit, are prohibited from entering or remaining in a safety zone except with the consent of the Health and Safety Executive or in accordance with regulations made under section 23(1) of the Petroleum Act 1987 (currently the Offshore Installations (Safety Zones) Regulations 1987 (S.I. 1987/1331)).
The United Kingdom Hydrographic Office (UKHO) (http://www.ukho.gov.uk/Pages/Home.aspx) publishes nautical charts covering the area in which installations are located, which include information on the existence and, where the scale allows, the location of safety zones. Mariners are advised to keep paper charts up-to-date using appropriate Notices to Mariners or, where electronic charts are used, to subscribe to an appropriate updating service. Vessels meeting the requirements of the International Convention for the Safety of Life at Sea 1974 will carry nautical charts and nautical publications (such as Notices to Mariners) to plan and display the ship’s route for the intended voyage and to plot and monitor positions throughout the voyage. This may be compulsory for some vessels, for example under the Merchant Shipping (Safety of Navigation) Regulations 2002 (S.I. 2002/1473). The UKHO also broadcasts Radio Navigational Warnings in relation to safety zones where updates to charts have yet to take effect and where installations are in transit.
Maritime safety information, which includes information on safety zones, is issued via the appropriate International Maritime Organisation, Global Maritime Distress and Safety System broadcast systems as defined by the World-Wide Navigational Warning Service.
It is estimated that the installations, which are not on station at the time of making this Order, will arrive at their stations at the approximate time set opposite their name in the table below:
Name of installation
Estimated arrival at station
Catcher Area Development Project, Burgman Field
1st May 2015
Catcher Area Development Project, Catcher Field
1st May 2015
Catcher Area Development Project, Varadero Field
1st May 2015
Cawdor Manifold and Production Wells
1st April 2015
Cayley/Montrose Intermediate Towheads
1st March 2015
Cladhan Field Development Project
1st May 2015
Flyndre Manifold and Production Wells
1st April 2015
Golden Eagle Northern Drill Centre
1st May 2015
Shaw Drill Centre
1st April 2015
Shaw Water Injection
1st April 2015
Western Isles SDC Development Project
28th February 2015

---
Source: https://www.legislation.gov.uk/uksi/2015/407 (the official version)
Page: https://openlegislation.uk/offshore-installations-safety-zones-order-2015
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.